Nakhodka Fertilizer Plant for 227 billion rubles prepares for launch
The Nakhodka Mineral Fertilizer Plant (NZMU), part of the Roskhim holding, plans to complete commissioning work in March 2027. The first phase is designed to produce 1.8 million tons of methanol annually, with private investment totaling 227 billion rubles, the Far East and Arctic Development Corporation (KRDV) said in the Far East and Arctic Development Corporation (KRDV).

Overall project completion has reached 95.2%. Construction and installation work has been completed, and the complex is mechanically ready. The plant is now carrying out commissioning work and preparing to receive natural gas.
«Preparation of NZMU for launch is proceeding on schedule. Construction and installation work was completed on time, and the plant has moved to the commissioning stage. All necessary infrastructure has been created,» said plant CEO Viktor Grebenyukov (quoted by KRDV).
Product shipments will begin in the first half of 2027.
The plant is being built in the Nakhodka Advanced Development Territory. The first phase will process 1.8 billion cubic meters of natural gas per year. In addition to the methanol unit, the complex includes eight tanks with a total capacity of 240 thousand tons and a marine terminal capable of receiving tankers with a deadweight of up to 53 thousand tons.
Production of mineral fertilizers is planned for the second stage. According to an NZMU statement on a contract signed in September 2026 with China Chengda Engineering, the capacity of the future complex will be 3.5 million tons of urea per year. The Chinese company is also the general contractor for the first phase. Construction of the methanol production facility is financed under VEB.RF’s Factory of Project Finance program in partnership with VTB. Nakhodka Mineral Fertilizer Plant
Investment in the second phase could exceed 600 billion rubles. According to KRDV, 1.5 thousand jobs are planned to be created by the launch of the two phases. Expected tax revenues to budgets of all levels will amount to 25 billion rubles over the period of tax incentives until 2036, and then 13.5 billion rubles annually. The gas transportation infrastructure built for the plant will also make it possible to expand gasification in Nakhodka.